A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- 4
- 5
- 6
- 8
Explanation
Let us Find the Work Rate Now, Let us Assume be the Number of Extra Days.
for
for